Port of Vancouver Unanimously Terminates Lease Early

Port of Vancouver Unanimously Terminates Lease Early
Oil train seen from Mitchell Point, Columbia River Gorge. (photograher: Joe Urmos)
February 27, 2018
Categorie(s): Latest News

This is a press release from the Stand Up to Oil coalition, of which Friends of the Columbia Gorge is a member. 

February 27, 2018 (Vancouver, WA) — Today, the Port of Vancouver voted to formally terminate its lease with Tesoro-Savage on February 28, 2018. This decision, agreed to by Tesoro-Savage, terminates the lease a month early and allows the Port to seek new tenants. With termination of the lease, the Tesoro-Savage oil shipping terminal cannot go forward. In his remarks to the Port Commissioners, Tesoro-Savage’s general manager stated that the company would donate its last monthly rent payment to community organizations.

In response, the Stand Up To Oil campaign issues the following statement:

“The Port and the people of Vancouver can now move forward and invest in infrastructure that reflects the community’s values and needs,” Rebecca Ponzio, Stand Up To Oil campaign director. “The Port’s action removes concerns about a lengthy appeals process and recognizes the broad and deep public opposition to the project.”
 

Recent Decisions

  • January 9, 2018: Port of Vancouver Initiates the project to rescind the Tesoro-Savage oil terminal lease: Stand Up To Oil press release
  • January 29, 2018: Governor Inslee denies the Tesoro-Savage oil terminal proposal: Stand Up To Oil press release

Review of Tesoro Savage EFSEC Process Timeline

  • August 2013: Initial Application submitted by Tesoro-Savage
  • January 2014: Application amended by Tesoro-Savage
  • May 2014: Land Use Consistency Hearing
  • December 2014: Tesoro preliminary EIS found inadequate
  • January 2015: Application amended by Tesoro-Savage
  • January 2015: Adjudication process officially commenced
  • November 2015: DEIS released for public comment
  • May 2016: Application amended by Tesoro-Savage
  • June-July 2016: Adjudication
  • October 2016: Application amended by Tesoro-Savage
  • October 2016: Stormwater Construction Permit released for public comment
  • May 2017: Notice of Construction Air Permit released for public comment
  • July 2017: Industrial Stormwater Permit released for public comment
  • November 2017: FEIS released
  • December 2017: Recommendation released
  • January 9, 2018: Port moves to rescind the lease
# # #